Your Cart
Certs-Pedia - Enjoy Special Discount Offer - Coupon code: → CP30OFF
Certs-Pedia - Enjoy Special Discount Offer - Coupon code: → CP30OFF

Free Practice Questions for PMI CAPM Exam

  The Certified Associate in Project Management Exam CAPM exam questions is the right choise to practice your PMI CAPM certification exam, In this PMI CAPM exam dumps you can get 1135 Questions to improve your skills and boost your success level in actual exam. The last update of Practice Questions is Jun 01,2025.
UNLOCK FULL
CAPM Exam Features
In Just $59 You can Access
  • All Official Question Types
  • Interactive Web-Based Practice Test Software
  • No Installation or 3rd Party Software Required
  • Customize your practice sessions (Free Demo)
  • 24/7 Customer Support
Page: 1 / 227
Total Questions: 1135
  • The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

    Answer: A Next Question
  • The process of identifying specific actions to be performed to produce project deliverables is:

    Answer: A Next Question
  • Completion of the product scope is measured against the product:

    Answer: B Next Question
  • The project manager implemented the stakeholder engagement plan and realized that some uploads should be made. Which components of the project management plan should be modified?

    Answer: C Next Question
  • Which of the following is an output from Control Scope?

    Answer: A Next Question
  • A company has implemented an adaptive project management framework for a new project. When planning for an iteration, how should risks be addressed? Choose two.

    Answer: A, C Next Question
  • On which type of project.... only after the final iteration?On wtiich type of project lite cycle is ihe deliverable produced trough a series of ileralrons considering thai the deliverable ts completed only after the Imal iteration?

    Answer: B Next Question
  • Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

    Answer: D Next Question
  • Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

    Answer: B Next Question
  • A project manager is working on project cost management. The following information is current.* Planned value = 30* Actual cost = 35* Earned value = 28Considering this data, which project indicator is correct?

    Answer: B Next Question
Page: 1 / 227
Total Questions: 1135