A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to compete m the marketplace1. What analysis should the team use to understand the issues?
A senior team member feels underutilized. What should the agile practitioner do?
A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?
During sprint retrospectives, some team members are very vocal and tend to dominate the conversation, while others are more reserved and less likely to participate. What should the scrum master do?
When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?
The project team is ahead of schedule and beginning to gold-plate the feature included in the current sprint. What should the agile project manager do?
The scrum master for a large project must provide an estimate of what can be delivered in six months. What should the scrum master do?
After completing the release plan, the team realizes that the project is very likely to have a negative ROI. What should the team do?
An agile project has three more iterations before the release. There is a lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports.What should the project leader do?