Free Practice Questions for PMI-SP Exam

  The PMI Scheduling Professional PMI-SP exam questions is the right choise to practice your PMI-SP certification exam, In this PMI-SP exam dumps you can get 326 Questions to improve your skills and boost your success level in actual exam. The last update of Practice Questions is Jun 01,2025.
UNLOCK FULL
PMI-SP Exam Features
In Just $59 You can Access
  • All Official Question Types
  • Interactive Web-Based Practice Test Software
  • No Installation or 3rd Party Software Required
  • Customize your practice sessions (Free Demo)
  • 24/7 Customer Support
Page: 1 / 66
Total Questions: 326
  • All of the following statements about the critical path are false except for which one?

    Answer: 4 Next Question
  • You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should be at the 45 percent milestone today, but due to some early delays you're running late. What is the planned value of your project?

    Answer: 3 Next Question
  • Which of the following characteristics of conflict and the conflict management process should be recognized by the project managers while handling conflict in a team environment? Each correct answer represents a complete solution. Choose all that apply.

    Answer: 1,,2,,3 Next Question
  • Holly is the project manager for her organization. Her current project is running late and her projectcustomer has asked Holly to find a method to apply corrective actions to the project schedule. Hollyis exploring the concept of crashing the project. Which of the followingstatements is true about crashing the activities in Holly's project?

    Answer: 2 Next Question
  • You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?

    Answer: 2 Next Question
  • You work as a project manager for Blue Well Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30. What does this figure depict?

    Answer: 4 Next Question
  • You are the project manager of the MQQ project. Unfortunately, this project is not performing welland you must do something to address theproblems in your project. Based on your planning for monitoring and controlling projectperformance, you know that there are three outputs ofperformance reporting. Which one of the following is the only output that is most appropriate forthis poorly performing project?

    Answer: 4 Next Question
  • What is the formula to find the schedule performance index?

    Answer: 3 Next Question
  • Gary is the project manager of the GHY project. He has elected to use a previous, but similar, project to guide him and the project team through the estimate activity duration process. The previous project schedule could best described as which one of the following?

    Answer: 1 Next Question
  • Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?

    Answer: 2 Next Question
Page: 1 / 66
Total Questions: 326